MicroStrategy - Project Administration

mstr

How can we unload a project?

  1. Launch Developer / Desktop
  2. Connect to appropriate project source
  3. Drill down on Administration -> Projects
  4. Right click on appropriate project
  5. Select "Administer Project -> Unload"

How can we load a project?

  1. Launch Developer / Desktop
  2. Connect to appropriate project source
  3. Drill down on Administration -> Projects
  4. Right click on appropriate project
  5. Select "Administer Project -> Load"

How can we configure a project to be automatically loaded on a particular server?

  1. Launch Developer / Desktop
  2. Connect to appropriate project source
  3. Right click on the project source and select Configure Intelligence Server
  4. Click on Projects -> General
  5. Click on appropriate check boxes next to the name of the project
  6. Click OK

How can we duplicate a project from one project source to another project source?

I was setting up a new DEV environment (or test environment) to handle the MSTR upgrade from 9.2.1m to 9.4.1. To duplicate a project from the existing DEV environment to the new DEV environment:

  1. Launch MicroStrategy Desktop 9.2.1m
  2. Connect to the existing DEV project source
  3. From the Schema menu, select Duplicate Project. Be careful. Before clicking on the Finish button, make sure that the options selected is appropriate. Make sure that we select "None" for "Users and user groups".

Follow the on-screen instruction. The process involves selecting the source project source (which is the existing DEV project source), and the destination project source (which is the new DEV project source), and a couple of screens. Go slow, and make sure you specify the right values / options.

  • TN12330 - How to duplicate a project in MicroStrategy Desktop 9.x